Grange Block B taking shape
JUNE 2026
Progress continues at Grange Road Block B, with current works focused on preparing the driveway area for the COA and EACC title application process.
On the housing side, exterior cavity works are now underway for Units 9–12. Building paper installation is approximately 70% complete, and the team is preparing to move into the interior first-fix stage shortly.
We will continue to provide updates as the development progresses.